Construction continues on the Kenmore-Jindalee Cross River Pipeline project.

The launch shaft in Kingfisher Park, Kenmore is now complete; and the shaft in Jindalee is also nearing completion at a current depth of 18 metres below ground level.

What's happening?

The sound-wall is now finished and the tunnel borer has arrived on-site in Kingfisher Park.

The tunnel borer is expected to be lifted into the launch shaft on Friday 24 March 2017, and it will take a few days to be assembled in the shaft before tunnelling begins.

24 hour, six days a week (6am Monday to 6pm Saturday) working hours are expected to start early next week (week commencing 27 March 2017). Residents will be notified in advance via postcard. 

Tunnel boring is expected take about nine weeks, weather and ground conditions permitting.

Community impacts
  • Construction noise in Kingfisher Park, including the operation of tunnelling machinery, truck movements including reversing safety beepers, and generators.
  • Dust may be visible during shaft excavation and backfilling activities and will be monitored and managed at source, using water suppression, as required.
  • Changed traffic conditions including reduced speeds on Gem Road and Sunset Road in Kenmore.
  • Lighting in Kingfisher Park during night works.
  • Increase in truck movements in Kenmore (please see truck route map below) with approximately 15 truck movements anticipated per day.

How will impacts be managed? 

We will work closely with residents impacted by construction during the project, as well as:

  • Monitoring noise levels to ensure work methods are appropriate.
  • A sound wall will be constructed around the worksite to suppress noise during night works.
  • Truck movements will be restricted to no later than 6pm daily to minimise noise during night work.
  • Directing site lighting away from residential properties.
  • Residents can call the project team at any time 24/7 on 1800 071 230 (free call) for assistance or information, or email community.feedback@urbanutilities.com.au.
  • Full restoration of Kingfisher Park, Kenmore and the area behind the Scout Hall in Jindalee, including landscaping will be carried out on completion of the project.

 

Residents can call the project team at any time 24/7 on 1800 071 230 (free call) for assistance or information, or email us at community.feedback@urbanutilities.com.au. 


Image: Shaft construction underway in Kingfisher Park, Kenmore 

    Image: Approximately 200 pipes ready for installation


     









    Work is underway on the Kenmore-Jindalee Cross River Pipeline to replace water and sewer infrastructure damaged in the 2011 floods and to ensure the sustainability of the network in the western suburbs.

    The major project includes the construction of water and sewer mains inside a tunnel that will be bored 10 metres beneath the Brisbane River, between Kenmore and Jindalee.

    Works on the project started in Jindalee in late August 2015. 

    We are aware of how highly you value your local park. We will ensure that any impacts on Kingfisher Park's amenity such as the removal of trees (approved by Brisbane City Council) to allow heavy vehicle access for deliveries and the removal of materials excavated from the tunnel will be addressed as part of site restoration at the end of the works.

    Installation valve chamber

    Installation of a valve chamber on Mt Ommaney Drive, Jindalee

    Start of the tunnel shaft construction

     

    Map of truck route from Kingfisher Park, Kenmore
    Did you know? Queensland Urban Utilities provides water and sewerage services to more than 1.4 million residents. We operate and maintain a vast network including 9000km of water pipes and 9000km of sewerage pipes.